Reading: The First Phase Of The Presidential Power Program Will Cost N991.99 Billion – FG
Share
Sign In
Notification Show More
Font ResizerAa
Phoenix RelationsPhoenix Relations
Font ResizerAa
Search
  • Home
  • About Us
  • Blog
  • Categories
    • Crime
    • Economy
    • Education
    • Entertainment
    • Health
    • Exclusives
    • News
    • Politics
    • Press Realeases
    • Sports
    • Tech
    • Opinions
  • Contact
  • Privacy Policy
Have an existing account? Sign In
Follow US
  • Advertise
© 2024 Phoenix Relations. All Rights Reserved.
Economy

The First Phase Of The Presidential Power Program Will Cost N991.99 Billion – FG

Phoenix Relations
Last updated: 19 June 2022 23:28
Phoenix Relations
Share
5 Min Read
SHARE

According to estimates acquired from the Federal Government, the overall financial requirement for the first phase of the Presidential Power Initiative is €2.3 billion (N991.99 billion at the official exchange rate of N431.3/€).

 

PPI is an initiative of the Federal Government conceived during a meeting between Nigeria’s President, Major General Muhammadu Buhari (retd.), and German Chancellor, Angela Merkel, on August 31, 2018.

 

It was conceived as a three-phase initiative to rehabilitate and expand Nigeria’s electricity grid through  improved generation, transmission, and distribution.

 

The Federal Government had to establish a special purpose vehicle, the FGN Power Company, to own and execute the PPI.

 

Data obtained in Abuja on Friday from the PPI Financing Structure document, put together by the FGN Power Company, showed that about 60 per cent of the €2.3bn would come from a consortium of German banks, while other financial institutions would provide the balance.

 

The document read in part, “The total project cost for PPI Phase 1 is estimated at €2.3bn in which about 60 per cent of the funds will come from the consortium of German banks to cover the offshore project cost.

 

The financing for the offshore   project will be sourced from German banks at   a concessionary rate, which will be covered up to 90 to 95 per cent by the Euler Hermes Aktiengesellschaft (German Export Credit     Agency).

 

“The remaining 40 per cent of funding for the transmission and distribution onshore works will be sourced from other financiers.”

 

It added, “FGN Power Company has already commenced engagement with the development finance institutions for mutual   collaborations on the required onshore funding.”

 

The company named some the DFIs to include the African Development Bank, Afrexim Bank, French Development Agency, as well as the European Investment Bank.

 

Nigeria’s power grid has been characterised by frequent collapse lately, plunging the country into darkness repeatedly.

 

The national electricity grid has collapsed about five times this year, twice in March and twice in April, before it recorded another collapse early this month (June).

 

To avert this and ramp up national power generation above the persistent average of 3,500 megawatts, the government in partnership with Germany came up with the PPI.

 

“The PPI is a government-to-government initiative, Nigeria and German government. It is being deployed in phases and we are now in phase one, to raise power generation to 7,000MW,” the Minister of Power, Aliyu Abubakar, stated at the recent Power Dialogue in Abuja.

 

He added, “We are taking up the transmission and distribution parts in phase one. So the distribution part is involved. We have a lot of transformers in it. The transformers are over 2,800 which are to be deployed nationwide.”

 

In the document obtained by our correspondent, the FGN Power Company said the PPI would modernise and upgrade power transmission and distribution infrastructure across the country by 2025.

 

“By investing billions of dollars into grid infrastructure, data systems, and skilled operators, the PPI will improve power delivery and spur economic  growth,” it stated.

 

The company added, “During Phase I, the PPI will focus on ‘quick-win’ measures to increase end-to-end operational capacity to 7GW (seven gigawatts). By the end of the PPI, the grid will reach 25GW capacity, therefore quadrupling today’s capacity.

 

“Given the existing challenge of capacity misalignment of the electricity grid, the PPI is undoubtedly an ambitious and challenging undertaking. As such, it needs careful shepherding and government-wide coordination.”

 

The firm stated that FGN Power Company was founded to fill that role to safeguard the success of the PPI.

 

This, it said, would be done by screening and selecting vendors, managing projects and coordinating stakeholders to ensure that the PPI projects finished with efficiency and optimise available capacity.

You Might Also Like

Nigeria’s fintechs hit a cross-border wall

Tegbe: Nigeria Mobilises New Investment, Super Grid Plans as Power Sector Enters Next Reform Phase

AFRICA IS NOT AT THE MARGINS OF ENERGY GEOPOLITICS; IT IS THE FULCRUM — TEGBE

Ondo State Launches 1,000-Hectare Coffee Plantation to Boost Exports

Domestic refiners in Nigeria bypass $3.13 billion in crude oil acquisitions as pricing disputes escalate.

TAGGED:Power

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.

By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Twitter Copy Link Print
Share
Previous Article INEC Has Yet To Make A Decision On Voter Registration Extensions
Next Article TINUBU TO BUHARI: YOU TRULY BELONG TO EVERYBODY, AND BELONG TO NOBODY
Leave a comment Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

//

We influence 20 million users and we are the number one  news network on the planet

Stay Connected

235.3kFollowersLike
69.1kFollowersFollow
11.6kFollowersPin
56.4kFollowersFollow
136kSubscribersSubscribe
4.4kFollowersFollow
- Advertisement -
Ad imageAd image

Latest News

Nvidia’s board is reportedly ‘not considering’ hiring Jensen
Default Blog 17 November 2026
EU Sanctions Pro-Russian Hacker Group and Propaganda Firm
Press Releases 17 November 2026
Lawyer on the microchip case passcode
Press Releases 17 November 2026
Power Minister Tegbe Reaffirms Tinubu Administration’s Commitment to Improved Electricity Supply
Press Releases 16 November 2026

Technology

  • Advertise with us
  • Terms & Conditions
  • Privacy Policy

Health

  • Advertise

Entertainment

Sign Up for Our Weeky Newsletter

Subscribe to our weekly newsletter to get our newest article/news/articles instantly!

Phoenix RelationsPhoenix Relations
Follow US
© 2024 Phoenix Relations. | All Rights Reserved.
Welcome Back!

Sign in to your account

Lost your password?